Excerpt from Practical Guide to SAP Profit Center Accounting by John Pringle.
Master data in PCA One way of classifying data in SAP is to differentiate between items that are considered master data and items that are considered transactional data. In SAP, master data is relatively static data that is usually defined once and is shared throughout the application. Examples include: vendors, customers, materials, general ledger accounts, cost centers, profit centers, etc. This master data is then used in transactional data such as invoices, billing documents, and material movements. In an SAP implementation project, the structure and definition of master data should be thoroughly planned to properly reflect the needs of the business. Careful consideration should be given to such factors as numbering and naming the master data, permitted field values, and the ultimate reporting aims of the business. In this chapter, I show the relevant master data available in profit center accounting.
Profit center As discussed in the previous chapter, the structure of the profit centers is meant to define a responsibility reporting view of the organization. Once the master data is defined, the profit centers are arranged in a hierarchy to represent the responsibility structure of the enterprise. During the design of the system, the nature of that responsibility structure should be determined. Along what lines does the business divide itself? Is it on a geographical basis, a functional basis, a product line basis, some other method, or a combination of some of the above?
Technically, the name of this hierarchy is defined first in the configuration settings and assigned to the controlling area before the profit center masters can be created. This is the case for both classic PCA and for PCA in the new GL. In classic PCA, it is also required to create a dummy profit center before you can start using the standard hierarchy. The concepts of dummy profit center and standard hierarchy are discussed more fully in the following sections.
The creation of the profit center master data is essentially the same regardless of whether you are using classic PCA or new GL PCA. Transaction KE51 is used to create profit centers (see Figure 2.1).
Figure 2.1: Create profit center initial screen
Set the controlling area Often, when entering transactions in the controlling module in SAP, you are presented with a preliminary screen asking you to enter the controlling area. Having to constantly enter the controlling area can become aggravating, especially when you may only be working with one area. The solution to this is to set your controlling area using transaction OKKS. Enter the controlling area that you work with and press the SAVE button. The value is now stored in your user parameters and remains until you set it to a different value.
It is important before you start creating pieces of master data, such as profit centers, to understand how you are going to name or number them. Unlike some master data objects in SAP, profit center numbering is not driven by a number range object. In fact, it is pretty much free form. You are limited by the field size of up to 10 characters and there are a few special characters such as * that will be rejected; otherwise you can use any alpha-numeric combination you choose. You should also be aware that the profit center, like the cost center, exists in the controlling area, so it is not possible to have a duplicate value within the same controlling area.
Since your profit centers will be tied in some way to other organizational objects in SAP, such as company codes and cost centers, it is prudent to have an overall numbering strategy for these objects before you start creating them in the system. This should reflect the responsibility structure of the organization and be designed to facilitate reporting. Often, the structure or the nature of your business will lead you to a certain strategy in profit center numbering:
In the fictional example, you are setting up profit centers for an organization that manufactures and sells toys and games. They are interested in looking at their results regionally. They operate in four regions; United States, Canada, Europe, and Asia. They are also interested in results by product line. These are: video games, board games, and card games.
Copying master data Many master data objects will have a COPY FROM or CREATE WITH REFERENCE option to allow you to use an existing piece of master data as a template for your new entry. This can significantly speed up the creation of new pieces of master data.
When you have decided on your profit center number, you can go ahead with transaction KE51 (see Figure 2.2).
The most important information about the profit center is contained on the BASIC DATA tab.
Figure 2.2: Create profit center basic data
The profit center is considered to be a time-based object in controlling, which means it is created with a validity period and you can create different data for different time periods. In configuration, certain fields on the master data can be flagged as time dependent, resulting in SAP storing a new master record whenever a time-dependent field is changed on a profit center. The ability to create time-based objects is a very important aspect of controlling since it allows you to view master data values at different time periods. For example, the person responsible for the profit center may change next year. If person responsible is a time-dependent field, then you will have a view of the profit center master when Sally was the person responsible, and then a new view starting when person responsible is reassigned.
Defining time-dependent fields Since every change to a time-dependent field causes SAP to write a new master record for the data object being changed, you should be very careful in defining fields as time dependent in the system configuration. By defining many time-dependent fields, the data volumes can become large and match-code searches can become confusing for the user, as a piece of master data with more than one time range will appear multiple times in a match-code search. The SAP-delivered configuration should be sufficient for most situations.
The time dependency of the profit center is checked when you create another object with a relationship to it, such as a cost center. If you created your profit center to be valid from 01/01/2015 onwards, you will not be able to create a cost center assigned to that profit center with a valid from date earlier than 01/01/2015.
Valid-from dates and other master data It is best to be aware of other master data requirements when you are setting up validity dates for profit centers, cost centers, and other CO objects. There may be requirements from other modules, such as HR or fixed assets, that the cost centers should exist for a certain time in the past to allow historical data to be loaded. It is good to know that before you create your cost centers and profit centers to avoid a lot of extra rework extending the validity periods after the fact.
Other key fields on the BASIC DATA tab are person respons, this is the person responsible for the results of the profit center. There is also user responsible, which links to the user master in the SAP system. This field is not mandatory since it is possible that the person responsible for the profit center does not exist as a user in the SAP system. The department field is a free text field that can be used to store an external department number. There is no validation on the entry in this field, so the user creating the profit center can enter any value they choose.
The field profit ctr group makes the link between the profit center and its place in the standard hierarchy. The profit center group selected here is a node in the hierarchy. In the initial setup of the profit center structure, there are several different approaches to populating this field. If you are creating other master data, such as material masters which may be dependent on a profit center number, you may want to load or create all the profit centers before you have fully thought out all the levels in the hierarchy. In this case, you may wish to create all the profit centers and assign them to the top hierarchy node and then distribute them later. Alternately, you may have your hierarchy in place and may choose to directly assign each profit center to its correct level during the initial creation. settings and assigned to the controlling area before the profit center masters can be created. This is the case for both classic PCA and for PCA in the new GL. In classic PCA, it is also required to create a dummy profit center before you can start using the standard hierarchy. The concepts of dummy profit center and standard hierarchy are discussed more fully in the following sections.
This book offers a comprehensive introduction to SAP ERP Profit Center Accounting (PCA) for both classic general ledger (GL) and the new GL. Get the tools you need to set profitability targets for business (planning) and then compare actual results against those targets to improve overall profitability. Solidify your understanding of the difference between PCA and SAP Controlling Profitability Analysis (CO-PA) views. Gain in-depth knowledge of the concepts, objects, and functionality available in PCA in SAP ERP, including the relevant master data set-up, actual data flows, planning scenarios, and reporting options. Clarify the differences between PCA and CO-PA and understand when it is best to use each. Dive into profit center transfer pricing and obtain detailed configuration and set-up steps required for activation. By using practical examples, tips, and screenshots, the author brings readers up to speed on SAP Profit Center Accounting.
– Fundamentals of SAP Profit Center Accounting (PCA) – Concepts, master data, actual data flow, and planning basics – Differences between PCA in classic and new GL – Reporting for Profit Center Accounting (PCA) Author John Pringle is the SAP FICO Competency Group Lead with Illumiti, a platinum SAP Partner and a leading SAP systems integration and management consulting company based in Toronto, Canada. He is the product owner for the SAP all-in-one Mining Solution, one of Illumiti’s all-in-one SAP solutions. John has been working in SAP consulting for over 15 years and has previously worked for PwC, IBM and Accenture. He has implemented SAP solutions in a number of industries including mining, automotive, food processing, semi-conductor manufacturing, and industrial and building products. He is SAP certified in CO and is experienced in implementing most areas within SAP FICO as well as areas in PS, MM, SD and PP. Prior to his consulting career John worked in a variety of business and accounting roles for over 10 years and has also been part of the client team in several large system implementations giving him a unique perspective on the issues faced by both consultants and the business. John has an MBA in Finance and International Business from Schulich School of Business in Toronto and is a CMA and CPA.